Title
|
Set Up and Realization of Constructions
|
Form of course completion
|
Exam
|
Form of course completion
|
Exam
|
Accredited / Credits
|
Yes,
4
Cred.
|
Type of completion
|
Combined
|
Type of completion
|
Combined
|
Time requirements
|
Lecture
2
[Hours/Week]
Tutorial
2
[Hours/Week]
|
Course credit prior to examination
|
Yes
|
Course credit prior to examination
|
Yes
|
Automatic acceptance of credit before examination
|
No
|
Included in study average
|
YES
|
Language of instruction
|
Czech
|
Occ/max
|
|
|
|
Automatic acceptance of credit before examination
|
No
|
Summer semester
|
2 / -
|
0 / -
|
0 / -
|
Included in study average
|
YES
|
Winter semester
|
4 / -
|
0 / -
|
0 / -
|
Repeated registration
|
NO
|
Repeated registration
|
NO
|
Timetable
|
Yes
|
Semester taught
|
Winter + Summer
|
Semester taught
|
Winter + Summer
|
Minimum (B + C) students
|
10
|
Optional course |
Yes
|
Optional course
|
Yes
|
Language of instruction
|
Czech
|
Internship duration
|
0
|
No. of hours of on-premise lessons |
|
Evaluation scale |
1|2|3|4 |
Periodicity |
každý rok
|
Evaluation scale for credit before examination |
S|N |
Periodicita upřesnění |
|
Fundamental theoretical course |
No
|
Fundamental course |
Yes
|
Fundamental theoretical course |
No
|
Evaluation scale |
1|2|3|4 |
Evaluation scale for credit before examination |
S|N |
Substituted course
|
None
|
Preclusive courses
|
N/A
|
Prerequisite courses
|
N/A
|
Informally recommended courses
|
N/A
|
Courses depending on this Course
|
N/A
|
Histogram of students' grades over the years:
Graphic PNG
,
XLS
|
Course objectives:
|
The students will understand the specific procedures for the preparation of constructions and their realization.
|
Requirements on student
|
Requirements for credit:
The student will elaborate and hand in a semestral project of an adequate level.
Credits from the subject KME/PŘS obtained in previous studies are not acknowledged
Requirements for exam:
Active knowledge of the content of the course, ability to apply the knowledge to solve practical exercises.
|
Content
|
1st week: Preparation and management by the supplier (construction company) ? steps to obtain a commission, participation in a selection procedure (offer-based or demand-based) done by the investor or developer.
2nd week: Preparation of an offer. Completion of a offer ? stating the construction?s price.
3rd week: POV ? plan of the organization of the building process, contract for work, payment calendar.
4th week: Realization of a construction ? main activities for the preparation of the production.
5th week: Site equipment. Handing over the building site, necessary energetic requirements, provisory objects, temporary public soil occupation.
6th week: Commissions ? activities of the sub-contractors, criteria for selection, deciding ? actualized time plan, budget.
7th week: Time plan of the construction. Operative management of the construction, operative plan ? necessary material, machinery and workers in time, dispatcher management. Specification of the preparation of the main types of constructions ? buildings, constructions for transportation, water constructions.
8th week: Active elements ? people directly influencing the management of the construction, duties of the project manager, of the main site manager, of the site managers, of the foremen.
9th week: Knowledge of the legal regulations and requirements for investment constructions ? main principles of work safety, environment protection, working with people, motivational approaches, the Labor Code and social problems.
10th week: Developer?s approach to the realization of constructions, project manager, principles for the evaluation of economic effectiveness of investments, total duration of the construction process (including costs for operating, reparations and removal of the construction).
11th week: Documents influencing the management of the construction. Construction diary, reports of the systems of quality management, work safety documents, environment protection documents, documents of the coordinator for work safety (act nr. 309/2006 of the Law).
12th week: Controlling the construction process ? production invoices, planned and real costs, necessary documents for claims, taking over and handing over the work, taking over and handing over the construction.
13th week: Final evaluation of the construction. Final calculation of the activities.
|
Activities
|
|
Fields of study
|
|
Guarantors and lecturers
|
-
Guarantors:
Ing. Petr Kesl, Ph.D. (100%),
-
Lecturer:
Ing. František Boháč, MBA (100%),
Ing. František Boháč (100%),
Ing. David Zdražil (100%),
-
Tutorial lecturer:
Ing. František Boháč, MBA (100%),
Ing. František Boháč (100%),
Ing. David Zdražil (100%),
|
Literature
|
-
Recommended:
Jarský Č., Musil F. a kol. Příprava a realizace staveb. CERM Brno, 2003.
-
Recommended:
Čápová, Tománková, Měšťanová. Příprava a řízení staveb. ČVUT Praha, 2007.
-
Recommended:
Tománková, Jaroslava; Čápová, Dana,; Měšťanová, Dana. Příprava a řízení staveb. Vyd. 1. V Praze : České vysoké učení technické, 2008. ISBN 978-80-01-04166-6.
-
Recommended:
Čápová, Tománková. Příprava a řízení staveb. Sbírka příkladů.. ČVUT Praha, 2008.
-
Recommended:
Kolektiv. Příručka rozpočtáře 2019, rozpočtování a oceňování stavebních prací. URS Praha,2019, 2019.
-
On-line library catalogues
|
Time requirements
|
All forms of study
|
Activities
|
Time requirements for activity [h]
|
Contact hours
|
52
|
Preparation for an examination (30-60)
|
35
|
Undergraduate study programme term essay (20-40)
|
20
|
Total
|
107
|
|
Prerequisites
|
Knowledge - students are expected to possess the following knowledge before the course commences to finish it successfully: |
know building materials and building structures at the level of subjects of construction and technology 1 |
know the building structure |
know the construction technology of buildings |
Skills - students are expected to possess the following skills before the course commences to finish it successfully: |
solve basic structures and technological rules of construction, implementation |
Competences - students are expected to possess the following competences before the course commences to finish it successfully: |
N/A |
|
Learning outcomes
|
Knowledge - knowledge resulting from the course: |
be familiar with the issues of preparation and implementation of constructions |
to apply basic legal norms, work safety and environmental regulations during construction |
apply the basics of the development approach to the planning and implementation of constructions, including the necessary macroeconomic assessments of projects |
be able to implement the preparation and operational management of buildings and development projects |
Skills - skills resulting from the course: |
to solve and design the preparation and implementation of the construction as a whole and its parts |
Competences - competences resulting from the course: |
N/A |
|
Assessment methods
|
Knowledge - knowledge achieved by taking this course are verified by the following means: |
Oral exam |
Seminar work |
Skills - skills achieved by taking this course are verified by the following means: |
Oral exam |
Seminar work |
Competences - competence achieved by taking this course are verified by the following means: |
Oral exam |
Seminar work |
|
Teaching methods
|
Knowledge - the following training methods are used to achieve the required knowledge: |
Lecture |
Practicum |
Skills - the following training methods are used to achieve the required skills: |
Lecture |
Practicum |
Competences - the following training methods are used to achieve the required competences: |
Lecture |
Practicum |
|
|
|
|